Wollam Construction completes simultaneous bridge replacement and water box culverts installation in under 90 days.
BRIDGE REPLACEMENTS
PROJECT OVERVIEW
project brief
UDOT started roadway improvements in Magna Utah by starting a bridge replacement project to address structural deficiencies on two different structures (035031F and 035033F). These structures are located on 9200 West near the Kennecott gate and 3500 South near 8900 West respectively in Magna. This work consisted of replacing both bridges, essentially simultaneously, which will provide new structures with a service life of 75 years each.
The project officially started on Jan 20th, 2020, reached substantial completion on April 17th, 2020, and finalized physical completion before May 17th, 2020. Other than a short punch list of items, the entire project was done within a 90-day window, under budget and ahead of schedule. On top of that, our team was able to build both box culverts and have them ready to receive water before March 31st , which allowed for the Utah & SL Canal Company to flow their irrigation water on time.
deliverables
-
Heavy Civil Construction
-
Underground Utilities
-
Pre-Cast Concrete Installation
-
Asphalt Paving
-
Ornamental Fencing
-
Landscape Restoration